3F. PRELIMINARY ESTIMATE
Mercy College Design Development Estimate
Victory Hall Addition / Renovation 07/26/17
Dobbs Ferry, NY
QUALIFICATIONS
1.0 Basis - This schematic drawing estimate is based upon the following information:
1.01 Mercy College Victory Hall Addition/Renovation Design Development drawings issued by Clarke Caton
Hintz dated July 10, 2017.
1.02 Mercy College Victory Hall Addition/Renovation Design Development specifications issued by Clarke
Caton Hintz dated July 10, 2017.
1.03 Mercy College Hillside Seating drawing L1 Layout, Materials and Grading Plan issued by Clarke Caton
Hintz dated July 15, 2017.
1.04 Mercy College Hillside Seating drawing LD1 Landscape Details issued by Clarke Caton Hintz dated July
15, 2017.
1.05 Current pricing and market conditions.
2.0 Exclusions - The following items are not included:
2.01 Design fees and other soft costs.
2.02 Liquidated damage costs.
2.03 Owner project administration costs.
2.04 Overtime and overtime premiums.
2.05 Utility company charges and/or fees.
2.06 Latent site conditions, including hazardous soil and contaminated groundwater remediation.
2.07 Testing of existing soil.
2.08 Costs incurred with employment and management of a Licensed Site Professional.
2.09 Rock or obstruction excavation, unless specifically identified.
2.10 Removal of underground fuel storage tanks.
2.11 Builder's risk insurance.
2.12 CM payment & performance bonds.
2.13 Subcontractor bonding.
2.14 Site Plan Approval processing and associated fees and levies.
2.15 Design contingency.
2.16 Security services during construction. (Temporary fence and lighting is included).
2.17 Full-sized mock-ups and associated costs not specified.
2.18 Relocation expenses.
2.19 Lightning protection.
2.20 Police details.
2.21 Indoor air quality control testing.
2.22 LEED accreditation expenses.
2.23 Window washing davits.
2.24 Door blocking.
2.25 Prime painting of structural steel.
2.26 Intumescent fireproofing.
2.27 Axiom trim @ acoustical ceilings.
2.28 Temporary heat and winter conditions.
2.29 AV design, equipment, installation & commissioning.
2.30 Scope associated with drawing C-102 Founders Hall Site Plan.
2.31 IT and Security wiring.