CONSTRUCTION SCHEDULING
Preconstruction Planning
KEYS TO Scheduling development begins with established interactive planning that
includes all team members.
SUCCESS:
• Strategy • Planning Meetings
• Identify Early Owner Milestones
• Experience • Set Design Document Time Frames
• Safety • Establish Procurement Dates of Subcontractors
• Proactive Th inking As the development of the schedule occurs during preconstruction, Barr &
Barr will work with the team to capture and include all activities that will
• Critical Decision aff ect the schedule.
Making CONSTRUCTION
Barr & Barr will manage the master schedule and ensure commitment from
• Eff ectively Working all parties. We will continuously review this schedule for possible impacts and
Tight Sites provide options to mitigate impacts should they occur. Commitment to the
master schedule is critical to achieve the established goal. Th e detailed master
schedule will include:
• Submittal development and approval.
• Fabrication/long-lead times of materials and equipment
• Logical plan to implement the work, tied to material availability
• Look-ahead schedules
• Equipment commissioning
• Start-up and training for users
• Desired owner occupancy dates
During construction, Barr & Barr will update the schedule on a monthly basis for
team review. Th is update will be published as part of the monthly status report.
LOGISTICS & SEQUENCING
A logistics plan is a dynamic document that brings together a culmination of
owner, design team and construction manager input to clearly document how
the project intends to proceed all while maintaining a separation of construction
activities from the public. Preliminary logistics plans start this process with
the initial thoughts and concerns of the owner considering the progression of
construction in the most economical, safe and effi cient manner.
• Develop Initial Plan Utilizing BIM
• Establish Times & Locations for Deliveries
• Create Weekly Look-Ahead Schedules
• Locate Storage & Staging Areas
• Build Comprehensive Safety Plan
- Work Hours
- Traffi c Patterns
- Parking
- Trucking Routes/Times
- Hoisting
- Staging
- Storage Areas