CONSTRUCTION SCHEDULING
                                               Preconstruction Planning
         KEYS TO                               Scheduling development begins with established interactive planning that
                                               includes all team members.
         SUCCESS:

          • Strategy                             • Planning Meetings
                                                 • Identify Early Owner Milestones
          • Experience                           • Set Design Document Time Frames

          • Safety                               • Establish Procurement Dates of Subcontractors

          • Proactive Th inking                As the development of the schedule occurs during preconstruction, Barr &
                                               Barr will work with the team to capture and include all activities that will
          •  Critical Decision                 aff ect the schedule.

             Making                            CONSTRUCTION
                                               Barr & Barr will manage the master schedule and ensure commitment from
          •  Eff ectively Working              all parties. We will continuously review this schedule for possible impacts and

             Tight Sites                       provide options to mitigate impacts should they occur. Commitment to the
                                               master schedule is critical to achieve the established goal. Th  e detailed master
                                               schedule will include:

                                                 •  Submittal development and approval.
                                                 •  Fabrication/long-lead times of materials and equipment
                                                 • Logical plan to implement the work, tied to material availability
                                                 • Look-ahead schedules
                                                 • Equipment commissioning
                                                 • Start-up and training for users
                                                 • Desired owner occupancy dates


                                               During construction, Barr & Barr will update the schedule on a monthly basis for
                                               team review. Th  is update will be published as part of the monthly status report.

                                               LOGISTICS & SEQUENCING
                                               A logistics plan is a dynamic document that brings together a culmination of
                                               owner, design team and construction manager input to clearly document how
                                               the project intends to proceed all while maintaining a separation of construction
                                               activities from the public. Preliminary logistics plans start this process with
                                               the initial thoughts and concerns of the owner considering the progression of
                                               construction in the most economical, safe and effi  cient manner.


                                                 • Develop Initial Plan Utilizing BIM
                                                 • Establish Times & Locations for Deliveries
                                                 • Create Weekly Look-Ahead Schedules
                                                 • Locate Storage & Staging Areas

                                                 • Build Comprehensive Safety Plan
                                                       - Work Hours
                                                       - Traffi  c Patterns
                                                       - Parking
                                                       - Trucking Routes/Times
                                                       - Hoisting
                                                       - Staging
                                                       - Storage Areas