Mercy College                                                                  Design Development Estimate
           Victory Hall Addition / Renovation                                                             07/26/17
           Dobbs Ferry, NY
                                                       QUALIFICATIONS
           3.0  Assumptions & Qualifications - The following stipulations are incorporated:

               3.01  We assume that on-site excavated material is acceptable to use for backfilling.
               3.02  We assume that winter conditions will not be required.
               3.03  We have included cementitious spray fireproofing at steel columns,  framing and bracing. Fireproofing of
                    metal deck and metal roof deck is assumed not to be required and is not included.
               3.04  Temporary utilities used during construction are assumed to be paid by owner.
               3.05  We assume that this project will not be applying for LEED accreditation.
               3.06  Final cleaning of building and exterior glazing is assumed to be by owner.

           4.0  Allowances
               4.01  Lump sum allowance for repointing 70 percent of brick masonry                   Not included.

           5.0  Alternates
               5.01                                                                                       $98,946
                    Provide additional precast hillside seating per add alternate on L1 Layout, Materials and Grading Plan