Page 9 - Barr&Barr_Technical Proposal
P. 9

Our monthly executive and budget reports were issued in a timely   and commissioning of the equipment.  Th  e system was delivered
        fashion. Barr & Barr updated the team on the project status of   to the site team for their installation.  Barr & Barr completed the
        fi nancials with fi nal projections, schedule, hot items, critical owner   building tie in and commissioning of the system.
        decisions, change order and potential exposures. We kept full
        transparency on all deliverables for the project to the owner.    Temporary Hot water system:  Th  e building hot water system was
                                                                 to work with a heat exchange provided by the Ground Source
         We produced a very detailed P6 schedule which refl ected not only   Heating System(GSHS).  Th  e GSHS was provided by a Cornell
        our activities but also the responsibilities of the design team and   vendor.  During the commissioning of the GSHS system in
        Owner highlighting critical milestone dates.  Early on our schedule   cooling mode, there was an anomaly in producing hot water.
        refl ected impacts such as late permitting, rock excavations and   Th  is directly aff ected Cornell’s ability to open their café as they
        discovered electrical and water services.  Th  e issuance of several   could not produce the minimum 100 degree water to satisfy
        bulletins and the incorporation of almost 500 ASIs made for   DoH.  While the design team, controls and  GSHS contractors
        challenges to keeping schedule.  Our schedule became fl uid to the   reviewed the system Barr & Barr off ered and implemented a
        ongoing design and owner revisions.  Our team, working hand in   solution to use a temporary hot water heater as the means to heat
        hand with the owner and architect, was the driving force behind   the water storage.  Th  e temporary system is currently in place
        the success of the project. We were very proactive in professionally   until permanent solutions are resolved.
        pushing the signature architect in meeting their time frames on
        deliverables and enforcing that the subcontractors were constantly   Photo Voltaic and Food Service:  Barr & Barr scope was expanded
        updated on the decisions. We were a constant force behind this   to oversee and manage the installation of the campus wide PV
        process, ensuring timely decisions in order not to impact our schedule.    installation as well as the Bloomberg café food service equipment.
        We were constantly tracking and updating the team on where and
        how the schedule was being impacted. Sequencing and recovery   Description of the coordination with adjacent developments
        options were always reviewed and discussed as a team.    or other concurrent projects. If applicable:
                                                                 Th  e Cornell Tech Project consisted of the coordination of four
        Our weekly foreman’s meetings maintained direct oversight keeping   Construction management fi rms on the 12 acre site.  Th ere were
        the pressure on the subcontractor base to maintain the quality,   several shared activities that had to be coordinated for successful
        compliance, proper manpower, safety. Weekly meetings were held   completion of the projects.
        with subcontractors reviewing safety; submittals and RFIs, manpower
        requirements, material delivery dates and logistics. Th  ree week look   Barging:  Th  e bridge accessing Roosevelt Island has limited
        aheads and critical milestones were reviewed and monitored.  MEP   capacity.  Also Cornell agreements limited use of the bridge
        meetings were held weekly to monitor the progress of the BIM model,   due to the sizeable construction project.   As a result equipment
        MEP coordination as well as the integration of the various systems.    and materials weighing more than 36 tons were barged to and
        Focused meetings were scheduled with the critical contractors to   from the Island.  Th  ere was a coordinated  eff ort between the
        the project.  For example there were bi monthly meetings with the   contracting teams to schedule materials such as steel, façade and
        façade and the electrical contractors ensuring the contractor was   mechanical equipment.
        on task and achieving milestones.  Our technology and supervision
        create very effi  cient and organized construction sequencing.  Site Logistics Meetings:   Coordination of the site was discussed
                                                                 at a bi-monthly Site Logistics Meeting.  Th  e Site Logistics meeting
        Description of Major Issues and how they were addressed:  was an overview of all the construction activities and included
        Th  e project encountered many major obstacles that were resolved   site safety, environmental, schedules, access and egress, barging,
        and/or mitigated by Barr & Barr with inclusion of the Design and   deliveries, and community events as general and weekly topics.
        Owner’s teams.                                           Site safety at each project as well as the site wide safety of the
                                                                 public segregated from construction was discussed.  An injury
        Bulletins & ASIs:  Th  ere were 11 Bulletins and close to 500 ASIs   logs were distributed at the meeting.  Environmental issues such
        that were incorporated into the documents.  Th  ough some ASIs   as dust migration and control, noise and light mitigation, and
        represented additional scope to the project some were also the   SWPPPs were agenda items.  An overall monthly schedule and
        completion of the architectural and MEP details.  Barr & Barr   look ahead was provided by each team member and incorporated
        off ered solutions to mitigate impacts by unforeseen conditions.    into master schedule.  A master schedule update was performed
        Rock removal:  Early on during the excavation process rock was   monthly.  Site access, snow removal, temporary facilities, parking,
        encountered.  Barr & Barr directed the contractor work 10 hour days   security were discussed.  Th  e coordination of equipment and
        and weekend to mitigate the rock removal.  Barr & Barr requested   material barging as well as delivery coordination ( ie. Concrete for
        the contractor bring a second drill rig to expedite caissons and piles   various sites) was implemented through daily requests including.
        thus recapturing some of the fl oat time lost during the rock removal.  As Roosevelt Island is an active destination with a vibrant
                                                                 community, an events calendar was shared denoting community
        Steel Sequencing:  Due to impacts of the rock removal, Barr & Barr   happenings.   A granular coordination of the site was held at a
        re-sequenced the steel fabrication in order to start the steel sequence   weekly Superintendent’s meeting.  Th  e agenda of this meeting
        concurrent with the completion of balance of foundation work.    was to organize fi eld eff orts and a weekly look ahead.

        Feature wall and Interior Glazing Structural Support:  Not all   Service Tie-ins:  Th  e Central Utility Plant and site work package
        the architectural component were coordinated with the structural   was the responsibility of another construction management
        drawings.  As a result there were two incidences where Barr & Barr   team.  Coordinated activities included the electrical, water and
        took the initiative to engage an engineer to review the conditions   sanitary and storm services and tie in from the CUP or from the
        and come up with the structural support systems required to install   site.   Campus wide low voltage requirements for telephone, data,
        the interior glazing at the gallerias and design a structural tube   security and fi re alarm were coordinated with Cornell and the
        system to support the atrium feature wall in the lobby.  other CM fi rms to ensure the campus is contiguous.

        Rainwater Harvesting Tank:  Th  e design and purchase of the
        rainwater harvesting tank required for the Bloomberg Center was
        stalled during site excavation.   Barr & Barr negotiated the purchase
   4   5   6   7   8   9   10   11   12   13   14