Page 20 - Construction Guide
P. 20
HEADSET
Once clean-up is complete, a superintendent from Thunderbird Pools will be on
site to do the head set for your In-Floor system. They will cut down the in-floor
pipes and glue the collars for the in-floor heads to be installed at start-up.
*Please note the actual in floor heads will not be installed until the pool is filled with
water at start-up, we have a special tool to install these and you will receive one with
your start-up kit.
ESTIMATED PHASE TIME: 1 DAY
PAINT/PREP FOR FINAL
If any painting is stipulated in the contract, a superintendent from Thunderbird
Pools will complete that at this phase in addition to installing the gate spring on
any pedestrian gate. You will need to verify child safety requirements for your
municipality and this must be completed if required. Please call the office to
verify child safety requirements 623-825-4422
ESTIMATED PHASE TIME: 1 DAY
-20-