Page 15 - Construction Guide
P. 15

SHOTCRETE




           Our shotcrete crew will pump in the concrete (like a firehose) to form

           the shell of the pool. This is a messy process and will need 48 hours to
           cure*. Thunderbird Pools will provide a sprinkler/timer** to aid with

           the curing process, (it will not run constantly) a superintendent from

           Thunderbird Pools will meet the crew to set up the sprinkler and

           check your job; they will pick up your shotcrete payment at this time
           (unless payment arrangements have been made with the office)



           *There will be a “kiddy pool” used to clean the shotcrete pump left on site and picked
           up at final clean up. This is a standard in the industry and a part of the shotcrete

           process.


           **If the sprinkler fails IT IS NOT AN EMERGENCY, please spray the concrete down
           with a hose if possible. If the pool shell (concrete) gets no water it is not a problem, we
           are trying to slow down the curing process for maximum strength but it is not a
           requirement.








































                     ESTIMATED PHASE TIME: 2 DAYS                PAYMENT DUE