Page 11 - Construction Guide
P. 11

PLUMBING/GAS




          Our Plumber comes in and lays all the piping for the pool, sets the

          equipment (pump, filter, heater, in-floor, etc.) and plumbs in vacuum
          breaker for AWL which is attached to the homes’   hose bib.




          Gas lines will also be installed by the plumbers at this phase if
          stipulated in the contract.




          All plumbing is kept under pressure until the deck is complete, the

          superintendent will continually monitor the pressure to ensure there
          are no leaks while building the pool.




          *Please note landscaping, irrigation and underground utility lines not
          marked or located by Bluestake are subject to damage at the homeowners
          expense










































                  ESTIMATED PHASE TIME: 2-3 DAYS        THUNDERBIRD POOLS SUPER ON SITE