ACRYLIC DECKING (IF REQUIRED)




          This is a 3 step process (form/pour/top) and the longest phase of construction.



          FORMING- Our deck crew will form the deck for the concrete pour, you will
          have a chance to look over the form and give approval or make changes before

          the deck is poured.  We do not form and pour the same day, the pour will be
          done the day after.



          POURING- The crew will prep the job before concrete is delivered, once the
          deck is poured it will need to dry for a minimum of 7 days before the acrylic

          topping can be installed. Please stay off the deck for at least 24 hours.


          TOPPING- After the concrete cures (7 days) the acrylic topping crew will come

          in to top (paint) the concrete with the acrylic lace color you have chosen. Please
          stay off the deck for at least 48 hours and be very careful for about 4 weeks.

          Topping is usually done after clean up to limit damage to the product.


            Once the deck is complete a superintendent from Thunderbird Pools will

              pick up your deck payment (unless payment arrangements have been
                                               made with the office)

































                     ESTIMATED PHASE TIME: 9 DAYS                PAYMENT DUE