PRE-GUNITE CHECK
A superintendent from Thunderbird Pools will come out prior to
calling the pool in for pre gunite inspection to verify the steel and
electric are installed correct per city code and pool plan. They will
clean up any debris left in the pool, if everything is approved by the
super, he will contact the office to be called in for the city inspection.
PRE-GUNITE CITY INSPECTION
The City comes out and inspects pool to make sure plumbing, steel
and electric are to code, we cannot request a specific time for
inspection so they will need open access. A member from Thunderbird
pools will be out to check the tag the day after inspection and set up
for shotcrete.
If the pool passes inspection (green tag) we will proceed directly to
the shotcrete phase.
If the pool does not pass inspection (red tag) corrections will be
required and it will be called in for re inspection, this may cause a
delay in the schedule.
*Please note some inspectors may be difficult to work with, we do everything
possible to make sure we work with them to keep your project on schedule the
best we can.
ESTIMATED PHASE TIME: 2 DAYS THUNDERBIRD POOLS SUPER ON SITE CITY INSPECTION