Page 208 - FreesStyler® Installation and Startup
P. 208

®
            INSTALLATION AND STARTUP


            Chapter 10 Initial Startup



            Startup Procedure
            Locate your supplied Programming Manual. Read and understand the following chapters:
               •   Programming

               •   General Machine Operation
               •   General Methods of Using Operator Interfaces
            You should also familiarize yourself with the standard user screens.

               MCC

               1)  Check power 208-230 V at MCC, 120V at SCC, proper voltage at Dryer panel, and optional wheel cleaner pump
                   panel. Note licensed electrician should perform.
               2)  Confirm that the power to the MCC is off at load center (building electrical Panel), then turn on all breakers, close
                   the door and turn on the disconnect.