MULTI-PURPOSE ARCH



                       Installation


                       Tunnel Placement
                       When placing a piece of equipment, tunnel depth will vary from site to  site.  Be  sure  to  allow  an
                       adequate operating envelope
                              1)  Once the MULTI-PURPOSE ARCH is fully assembled, stand it up in the appropriate location and
                                 lag the driver side leg to the floor.












                                                                Direction
                                                                  of
                                                                 Travel







                                                  45”


                                                               Overhead View
                                       Dimensions are taken from the outer equipment leg to the driver side edge of the inside guide rail
                              2)  Confirm that the legs are  evenly spaced at the top and bottom  and  the Arch is level in both
                                 directions. Lag the other side to the floor.









                                                   Be sure legs are spaced the same at top and bottom








                                                   Be sure legs are spaced the same at top and bottom


                              Note:  Make sure that the MULTI-PURPOSE ARCH is  level.  Check  that there is an equal
                                     measurement from the driver’s side to the passenger’s side at both the top and bottom of
                                     the MULTI-PURPOSE ARCH legs.