Installation
Leak Test and Pendant Installation
1) Run water through the both manifolds of the Arch and verify there are no leaks in any of the fittings.
2) Locate the supplied plastic pendant cap. Stretch it open and position it into place as shown below.
3) Locate the supplied tie-wraps and loop them through the holes in the top of the pendant as shown
below.
Pre Soak Valve Assembly Installation
1) Remove the components shown below from the upper manifold and install the Pre Soak valve
Assembly also shown below.
NOTE: Be sure to
mount the Valve
Assemblies in
opposite
Feed Hoses directions as
shown so that
Hose Clamps they will fit into
place properly
Nipples Plumbing will be
covered later in
this document
Foam Spacers
Before After
1MANUL115 Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (810) 349-7010 * Fax (248) 380-9681 17