                       Installation


                       Additional Options: Foam Pods

                          Single Foam Pods and Triple Foam Pods
                              5)  Utility Arch-Triple Foam: Mount it to the head beam at the distance shown below using
                                 the wedge plate and 1/2-13 fastener.  The six tees are to face the exit of the arch.


                                                             Before      After
                                                      3-1/2“






                                 Spray Arch-Triple Foam: Mount it at the location shown in the images without using the
                                 wedge plate and 1/2-13 fastener as shown below.
                                     •   Remove the 1/2-13 hex head bolt and the ½” lock washer from the Triple Foam block
                                         assembly
                                     •   Remove the 3/8-16 button head fastener from the frame (shown in the image below-left)
                                     •   Use a field supplied 3/8-16 x 2”fastener with a 3/8” flat and lock washer to secure the
                                         maifold to the arch frame. Be sure to use the wedge-plate as a spacer between the arch
                                         and the manifold
                                     •   The six tees are to face the exit of the arch.


                                                         Remove the      After
                                                            fastener
                                                             circled
                                                             below






                              6)  From the center feed assembly, you will run the supplied 1/4” airlines to each side of the
                                 Arch for the air and for the water/chemical feed.

                              Note:  If the foaming pods have been mounted to a LED Neon Spray Arch, the 1/4” airlines will
                                     have to run and be secured in the field on the exit side of the head beam and legs.

                              Note:  Steps 7 thru 15 only apply to foaming pods that are mounted to a Neon Utility Arch.
                              7)  Locate the three, one foot sections of nylon protective sleeve from the accessory box.




                                                      .
                                 You will use two of the sections at each corner of the head beam. The third will be used
                                 at the point where the airlines will come out of the filler strip at the upper portion of each
                                 leg.