Page 14 - Prep Jet System
P. 14
PREP JET SYSTEM
Initial Startup
This Section Critical to Proper Operation
CAUTION
THOROUGHLY WIPE DOWN ALL INTERIOR SURFACES OF THE TANK AND MAKE
SURE THERE IS NO INSTALLATION DEBRIS IS LEFT BEHIND.
1) Open shut-off valve to inlet plumbing. Operate Hydro minder™ manually (fully off to fully on)
several times prior to allowing water to reach maximum level.
Note: The Hydrominder will be slow to react the first time it is shut off. This is normal.
2) Close shut-off valve and visually inspect bottom of tank for any debris which may have been
accumulated in the inlet plumbing installation. Clean tank if necessary.
3) Re-open shut-off valve and allow tank to refill.
4) Fill the oil reservoir to the proper level using the supplied CAT™ Oil. The correct level is when the
oil reaches the halfway point of the red dot in the middle of the sight gauge.
Oil Filler Cap
Oil Sight-Gauge
5) Replacement oil can be acquired through your distributor or Belanger, Inc.
6) Make sure that the unloader valve is set to start under minimum pressure by turning the
adjustment nut “Out”.
Adjustment Nut
Note: As the adjustment nut is turned out, the pressure is lowered, just as when turned in, the
pressure is increased.
12 Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681 1MANUL603