WASH AROUND



             Installation


             Tunnel Placement
             When placing a piece of equipment, tunnel depth will vary from site to site. Be sure to allow an adequate
             operating envelope
                1)  Lower the assembled unit in its permanent location.

                2)  Level the unit in both directions and lag to the floor.
                                                  CAUTION

                                 On all 28” “Wide Based” legs, secure lag bolts in all of the holes.

                                                     Overhead View

                                                      Center
                                                       Line






























                                                    DIRECTION
                                                        of
                                                      TRAVEL







                            45”

                                The 45” dimension is taken from the inside edge of the inside conveyor guide rail to the outside edge of the equipment leg.