Page 24 - Top Wheel Signature® Series
P. 24
SignatureSignature SeriesSeries
TOP WHEEL SignatureSignature ® SeriesSeries
Installation
Frame Assembly
Erecting the Frame
1) Locate the shipping skid that the unit arrived on and slide it under hub the assembly. Clamp
the Top Wheel to the skid.
CAUTION
Be sure to clamp equipment securely to the forks of the forklift.
Do not stand under load while forklift is in operation.
2) Slowly raise the skid until the legs are hanging in a vertical position and move the unit into its
tunnel location.
3) Anchor driver side leg to the floor keeping in mind the required operation space for other
tunnel components.
4) Measure distance between the upper and lower legs. Make sure the frame is square and lag
the passenger side leg to the floor.
20 Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681 1MANUL752