Page 24 - Top Wheel Signature® Series
P. 24

SignatureSignature   SeriesSeries
            TOP WHEEL SignatureSignature  ®      SeriesSeries

            Installation


            Frame Assembly

                Erecting the Frame
                1)  Locate the shipping skid that the unit arrived on and slide it under hub the assembly. Clamp
                   the Top Wheel to the skid.
                                                 CAUTION

                      Be sure to clamp equipment securely to the forks of the forklift.
                            Do not stand under load while forklift is in operation.

                2)  Slowly raise the skid until the legs are hanging in a vertical position and move the unit into its
                   tunnel location.






















                3)  Anchor  driver  side leg to the floor keeping in mind the required operation space for other
                   tunnel components.
                4)  Measure distance between the upper and lower legs. Make sure the frame is square and lag
                   the passenger side leg to the floor.