Page 14 - Wave Across™ Signature® Series
P. 14

WAVE ACROSS™ Signature ® Series


             Installation

             Frame Assembly

                The Head Assembly has the water manifolds secured into place at the factory. Determine which
                side has the main water feed and be sure that side is oriented on the side of the utility room. See
                image below.













                1)  Place the head assembly in its approximate tunnel location. Using a forklift, strap the head
                    assembly securely to the forks and raise above the height of the support legs.
                    Note:  Be  sure  to  clamp  or  strap  equipment  securely  to  the  forks  of  the  forklift  before  lifting
                           equipment. Do not stand under load while fork lift is in operation

                2)  Locate the leg assemblies and the following fasteners.
                       1/2-13 x  6-1/2” bolts (8)  1/2” lock washers (8)   1/2” flat washers (16)   1/2” nuts (8)
                3)  Secure the legs to the head assembly as shown below.