Page 29 - Top Wheel Mix & Match
P. 29

TOP WHEEL Mix and Match


                      Installation


                      Frame Assembly

                          Erecting the Frame
                          1)  Locate the shipping skid that the unit arrived on and slide it under the hub assembly. Clamp
                             the Top Wheel to the skid.




                                Be sure to clamp equipment securely to the forks of the forklift.
                                      Do not stand under load while forklift is in operation.
                          2)  Slowly raise the skid until the legs are hanging in a vertical position and move the unit into its
                             tunnel location.





















                          3)  Anchor  driver  side leg to the floor keeping in mind the required  operation space for other
                             tunnel components.
                          4)  Measure distance between the upper and lower legs. Make sure the frame is square and lag
                             the passenger side leg to the floor.





























                       1MANUL749            Belanger, Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681        25
   24   25   26   27   28   29   30   31   32   33   34