Page 9 - NSFP Waste to Energy Solution 080218
P. 9

250  8  24  12  24  50  2  1
























                   Working days / year Working hours / day for sawmill Working hours / day for gasifiers Working hours / day for pellet line (nightshift) Working hours for belt drier  Wood chip and sawdust m.c. green %  Gasifier will use 0.73kg pellets / k/w 1kg water evaporated requires approx. 0.9kW Th energy Burkhardt gasifier will consume 120kg pellets / hr. Gasifiers will generate 780kwTH / hr.  Drier requires 1.8MWTH / hr. Surplus heat energy from TAAnn is required

            SOUTHWOOD ENERGY MASS BALANCE








                     7.0  2.5  4.3  1.6  5.89  Wood chip and sawdust m.c. dry %
                   T / hr
                     56.0  20.0  34.7  12.4  47.12
                   T / day

                     14000  5000  8680  3100  11780
                   T/ p.a.









                 ASSUMPTIONS  Wood waste volumes   Wood chip (green)  Sawdust (green)  Wood chip (dry)  Sawdust (dry)  Total raw material
   4   5   6   7   8   9   10   11   12   13   14