IAAF W ORLD U18 REPORT
Milestones
e table below outlines the major milestones that were set out for the Nyayo village project.
Actual Date Of
Milestone Remarks
Completion
A Sample room/ Washroom
Construction of a sample room and a sample washroom and Jan, 2017 was done and approved
approval from LOC/ IAAF before executing the rest of
KYEB
the work
Removal of existing fl oor tiles/ Pvc tiles
Completion of Nyayo Hostels 1 to 6 (Including Mechanical
June, 2017
and electrical works, Installation of solar water heating
system, Firefi ghting system, waterproofi ng, ICT network)
Completion of Nyayo Annex Flats (Anti-doping and Health
June, 2017
Unit)
Complete of Common Room 1 (Entertainment area) and
Common Room 2 (Athletes Massage area Board rooms and
Communication Centre)
Complete of Nyayo Kitchen including equipping and
July, 2017
extension of ablution block. June, 2017
KENYA YEARBO0K
July, 2017
Completion of a Police post
Refurbishment of the accreditation centre
External works (including landscaping, storm water
EDITORIAL BOARD
June, 2017
drainage, perimeter wall, walkways, ICT fi bre optic cabling)
June, 2017
Street Lighting and Roads accessing the Nyayo Village
Construction of a footbridge across the Railway line NIL Works at 75%
Civil works complete
Supply and installation of all Tartan track including awaiting installation of the
associated civil works. NIL tartan. Overall completion
– 85%
ACTIVITIES AND OCCURENCES DURING WORLD U18 CHAMPIONSHIPS | 181