        Objectives                         To solve the problem of water deficiency and disruption of clean water supply.
        Methodology                         Sourcing for groundwater and treat the water to meet the standard for domes-
                                            tic usage.
        Activities Conducted                Development of groundwater treatment system.

        Output
         Industry                           Continuous clean water supply.
        Public Higher Learning Institute   Acknowledgement on the technology’s workability and reliability by the heads of
                                           communities in the project area.
        Human Capital Development          Two (2) graduate interns managed to develop the designed system to cater the
                                           community’s need.

                                           The interns have as well receive exposure to communicate and train community
                                           to handle and manage the system.



                                                                                        PROBLEMS IDENTIFIED





                                                        1.     Inconsistent rainwater supply.

                                                        2.     Unclean water source.


                                                                                                                 44


    KNOWLEDGE TRANSFERRED





         1.      Method on sourcing for underground water.

         2.      Method on underground water treatment.

         3.      Method to manage and maintain water filtration system.






                                                                                               FINANCIAL
                                                                                            INFORMATION




          ITEMS         KTP GRANT        KTP GRANT        UTILISATION         CONTRIBUTION
                            (RM)          BALANCE        PERCENTAGE                FROM
                                             (RM)              %              INDUSTRY (RM)

        AMOUNT           153,404.55       153,404.55           100.00             5,000.00