Criterion 5 Scope of Work
Project Scope
SECTION 6. Project Pricing
The price for the work described above is as follows:
Cost of Work ........................................................................................... $ 9,837,000.00
General Conditions .................................................................................. $ 598,000.00
Pre-construction EDI ................................................................................ $ 111,000.00
Fee (10.5% of COW)................................................................................ $ 1,144,233.00
Total Project Cost .................................................................................... $ 11,690,233.00
Site Allowance (included in cost of Work) ................................................... $ 50,000.00
*Breakdown pricing is for accounting purposes only and shall not be interpreted as standalone
pricing or used for construction breakdown.
*This proposal is void and may be withdrawn if not accepted in writing or a contract agreeable to
both parties cannot be negotiated within 30 calendar days of this date. Unless otherwise stated
above, no provisions for price escalations have been included in this proposal. This price may be
subject to escalations after the void date.