Page 34 - Trail Winds Proposal E2
P. 34

Criterion 5                                                          Scope of Work



         Construc.on



          SECTION 4. General Qualifica-ons:



         10. Elements excluded from this proposal:

                a)  Con.ngency fees or allowances.

                b)  Cable Trays

                c)  Pain.ng of exposed raceways and electrical equipment, or removal of hangers and straps to ac-
                   commodate pain.ng

                d)  Cost associated with liquidated damages if applicable and if values are not disclosed within the bid
                   documents

                e)  Cost and labor hours for background check if requirements are not provided within the bid docu-
                   ments


                f)  Installa.on, offloading or handling of Owner Furnished equipment
                g)  Any cost associated with hospital personnel being present during shutdowns, over.me, shiH work

                   or as escorts

                h)  Transporta.on of owner’s salvaged equipment to an off-site loca.on
                i)  Transporta.on of owner furnished products to the project site

                j)  ”Hot work” on energized circuits or equipment, regardless of size



       Tri-City Electrical Contractor, Inc.  |  Electrical Proposal


          SECTION 5. Project Specific Scope of Work:




                   General Scope:
                   Engineering fees                                  X
                   Utility installation fees, costs, deposits        X
                   Electrical permit fees                      X          Included with building permit.
                   Material and personnel hoisting             X          Hoistways provided & operated by others.
                   Trash and debris removal                    X          To FBO on site dumpster.
                   Composite clean-up crew                           X
                   Hazardous waste disposal                          X
                   Traffic control                                   X
                   Access panels                                     X
                   Pollution insurance                         X
                   Stretch and flex                                  X




     33                 Tri-City Electrical Contractor, Inc.  |  “To Do More Than Expected”  |  www.tcelectric.com
   29   30   31   32   33   34   35   36   37   38   39