Criterion 5                                                          Scope of Work



         Construc.on



         SECTION 1. Summary of the Work:






         Our proposal is based upon the current RFP Desingn Narra.ve, drawings and specifica.ons.    The overall pro-
         ject scope includes 170,000 sqH of structure for the new hospital, new CEP and site work.  This proposal is
         based upon construc.ng the en.re project in a LEAN method to reduce overlap in scope and provide the ut-
         most quality.









         SECTION 2. RFP Documents:



         MEP RFP Ocala Trailwinds                                 9/14/21

         Final Dev Package                                        02/03/21

         EDI Checklist                                            03/24/21

         Trailwinds MEP RFP Schedule                              09/24/21

         Start-up Package with Sample Subcontract                 N/A

         Construc.on Condi.oning – V3.0                           N/A

       Tri-City Electrical Contractor, Inc.  |  Electrical Proposal  Duct Cleanliness – V3.0
                                                                  N/A







         SECTION 3. BIM Coordina-on:





         BIM or clash detec.on coordina.on is included for major elements of the electrical package