412   |  ChaPter  10  Working With Phasing, grouPs, and design oPtions



                        Figure 10.80
                        set the sorting/
                        grouping options
                        for the demolition
                        schedule.



























                        Figure 10.81
                        The completed
                        wall demolition
                        schedule



















                             At this point in the exercise, you can drag the floor plan views, 3D views, and schedules from
                           the Project Browser onto sheets for publishing, as shown in Figure 10.82. We’ll cover sheets in
                           greater detail in Chapter 17, “Documenting Your Design,” but for now you can begin to become
                           familiar with the process. Add the plans, 3D views, and schedule for Phase 1 to sheet A101, and
                           then add the views for Phase 2 to sheet A102.











          c10.indd   412                                                                             5/3/2014   11:05:07 AM