Page 35 - AZ - City of Tucson Fire Station 8 Rebuild
P. 35

ROLE OF TEAM MEMBERS                                                  REFERENCES


        Senior Project Manager: Fred Knapp                                    Northwest Fire District
        Project Manager: Sean Mulvanny                                        Heather Ruder
        PreConstruction Manager: Mireya Ramirez                               Facilities Manager
        Superintendent: Jose Acosta                                           P: (520) 887-1010
                                                                              E: hruder@northwestfire.org
        PRECONSTRUCTION SERVICES                                              WSM Architects, Inc.

                                                                              Paul Mickelberg
        Estimating, scheduling, value engineering, quantity take-offs,        Principal
        constructibility reviews, options studies, virtual design (BIM)       P: (520) 408-1044
                                                                              E: pmickelberg@wsmarch.com
        ORIGINAL/FINAL CONSTRUCTION COST

        Fire Station No. 337: $3,876,695 | $3,986,768
        Fire Station No. 341: $3,876,695 | $3,986,768


        CONSTRUCTION DATES


        Fire Station No. 337: December 2018 - October 2019
        Fire Station No. 341: December 2018 - October 2019


        OWNER


        Northwest Fire District



        CORE - CITY OF TU CSON FIRE S TATION NO . 8 REB UILD PR O JEC T                                    PAGE 35
   30   31   32   33   34   35   36   37   38   39   40