Page 37 - AZ - City of Tucson Fire Station 8 Rebuild
P. 37
ROLE OF TEAM MEMBERS REFERENCES
Senior Project Manager: James Faria Daisy Mountain Fire District
Project Manager: Sean Mulvanny Jon Binsbacher
PreConstruction Manager: Leroy Trujillo Fire Captain
Superintendent: Steve Brandon P: (623) 810-1550
E: jon.binsbacher@dmfd.org
PRECONSTRUCTION SERVICES Sun City Fire District
Ron Deadman
Estimating, scheduling, value engineering, quantity take-offs, Fire Chief
constructibility reviews, options studies, virtual design (BIM) P: (623) 293-3614
E: rdeadman@suncityfire.com
ORIGINAL/FINAL CONSTRUCTION COST
$5,997,974 | $5,898,657
CONSTRUCTION DATES
March 2016 - August 2018
OWNER
Daisy Mountain Fire District
CORE - CITY OF TU CSON FIRE S TATION NO . 8 REB UILD PR O JEC T PAGE 37