Page 53 - Megaprojects Playbook
P. 53

PHASED GMP SUBMISSIONS FOR EPC WORK   DIAGEO: KEY PERSONNEL

 Multi-disciplinary scope (facility, process, utilities & packaging) means we were responsible for the ripple
 effects of changes between the scopes. When Haskell does not own the total scope, a variance to a piece of
 packaging equipment (example: foundation or utility load) is passed back to the owner as a change order when
 the change becomes known. When Haskell owns the total scope we're responsible for all of these variances
 inside of our contract value, because we've committed to a GMP that incorporates contingency to manage all
 of these changes. Consider phased GMPs by scope of work based on design completion. Adapt contingency   Process Development
                                                         Relay, Maryland
 to adequately address the risk of unforeseen changes that would not come through as a contract
 change. Determine the appropriate levels by a risk review based on the level of scope completeness.

 OWNER ASSIGNMENT

 When Haskell agrees to incorporate equipment previously purchased by the client in our contract scope, we take on
                   DESIGN/ENGINEERING                 PROJECT MANAGEMENT                 PROGRAM RESOURCES
 all risks of outcome even if we weren't initially responsible for the error. The Brenton Case packer was an unproven
 technology for the application. It was selected and purchased initially by Diageo. We accepted the equipment into   project principal plainfield  senior project manager  program executive
 our contract, but advised that there was a high risk (both likelihood and impact) that the technology wouldn't   Peter Skirbst, AIA  Matt Lantzy  John-Paul Saenz
 work. The technology indeed did not work. However, because we accepted the scope inside of our contract we   project principal  program director
 were responsible to make the necessary modifications and repairs, which resulted in high costs and ultimately   David Kode, AIA  Tom Van Ness
                                                        EXECUTIVE STAFF
 damaged our reputation. Only accept assignment of owner purchased equipment if you can carve the risk out   process + utilities lead  director of construction
 of the contract and/or have an opportunity to validate that it is the right application for our scope of work.  Barnum Mechanical, Inc  project manager  Jerry Langford
                                                          Anthony White
                       packaging lead                                                     director of procurement
                       Tom Van Ness                    construction manager                   Jonathan Toke
                                                           Tim Coons
                      project architect
                                                        field project manager
                       Daniel Aguilera
                    Amber Edington, LEED AP               Matthew Craft
                      civil engineering                  quality assurance
                        GW Stephens                       coordinator
                      **Mike Wheeler, PE
                                                         Michael Wittmann
                    structural engineering              field project manager
                       Joe Watson, PE
                                                           Chris Callura
                    mechanical engineering            Project Manager Packaging
                       Dana Helman, PE                    Jeremy Triplett
                    electrical engineering
                       Gerry Lukach, PE
                     landscape architect               Trade Subcontractors
                        GW Stephens
                      **Erick Lycke, ASLA

























                                                                                                     **Haskell Peer Review Team
 HASKELL | WE CREATE THINGS THAT MATTER                                                                            47
   48   49   50   51   52   53   54   55   56   57   58