Page 49 - Megaprojects Playbook
P. 49

LESSONS LEARNED


                        LOOKING AT OUR PAST FOR A BETTER FUTURE

                       As move forward with our new Mega Project strategy it is important to also look to the past. We present you
                       with case studies of three prior large scale projects completed in the last 10 years. Each project was different in
                       delivery method, contract type and had different challenges to overcome. Most importantly, each project had
                       lessons learned that came from the project upon completion. There are some similarities and differences between
                       the lessons that were extracted from each project, but ultimately a summary of important program-focused
                       lessons were identified for each project and are listed in each case study to assist in developing future projects.


                           1      DIAGEO LINE (Q3 2010 - Q4 2013)



                                  The Diageo line strategy project was a transformation of Diageo’s bottling supply chain in North
                                  America. Diageo is the world’s leader in spirits sales, capturing more than 30% of the global market.
                                  Their manufacturing footprint was the result of multiple purchases and mergers over the course
                                  of the 20 years prior to the project. As a result, most of the bottling infrastructure was aged and
                                  redundant with infrastructure available at other existing manufacturing sites. Diageo evaluated
                                  all their bottling facilities and lines in North America and scoped an optimization project that
                                  consolidated sites and replaced existing packaging lines with modern and more efficient bottling
                                  lines. This allowed them to eliminate two sites and the costs associated from their manufacturing
                                  footprint, while driving down their costs percase of bottled spirits through efficiencies in both
                                  the new bottling lines and efficiencies gained in production scheduling with the new footprint.
                                  Diageo redistributed the SKUs of their most popular products across two facilities. This included
                                  new packaging lines, decommissioning of old facilities and packaging lines, and the facilities and
                                  blending upgrades required to support the new packaging lines. The project reduced the number of
                                  bottling facilities from four to two and reduced the total number of packaging lines from 21 to 11.


                        SPECIFICATIONS                               SERVICES



                            ◆  650,000 SF Building                         ◆  Complete AE Design
                               – 38,000 SF Bottling Hall Renovation - Relay    ◆  Construction Project Management
                               – 8,000 SF Bottling Hall Expansion - Relay    ◆  Process Engineering
                               – 22,200 SF Warehouse Expansion – Plainfield    ◆  Permitting & Construction Management
                               – 18,300 SF Process Expansion - Plainfield    ◆  Equipment Procurement & Installation
                               – 46,400 SF Bottling Hall                   ◆  Process and Packaging Installation
                               Expansion - Plainfield
                                                                           ◆  Start-up & Commissioning
                               – 23,000 SF Semi-Works Bottling             ◆  Operation & Maintenance Training
                               Renovation – Plainfield
                               – 10,000 SF Tank Farm Expansion - Plainfield
                            ◆  10 Miles of Stainless Steel Pipe
                            ◆  11 New Packaging Lines

                            ◆  142,000 MHRS Engineering and
                             Project Management






        44                                                                               MEGA PROJECTS PLAYBOOK | 2021
                                CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION.  FOR INTERNAL HASKELL USE ONLY.
   44   45   46   47   48   49   50   51   52   53   54