Page 51 - Megaprojects Playbook
P. 51

Diageo Line



            LESSONS LEARNED









                 CONTRACT SCOPE DEFINITION

                 Detailed scope was not defined when contract price was set. Further, the client's project team did
                 not have authority to approve cost changes but were held responsible for delivering the scope of
                 work. This led to the client attempting to add scope to the project without a corresponding contract
                 increase. The misalignment of authority and responsibility led to challenges between the project
                 teams, which added obstacles to completion. Review detailed scope of work for clear understanding
                 with the clients executive and project teams prior to finalizing the contract price.


                 END USER PARTICIPATION THROUGH DESIGN

                 The project scope was developed with Diageo's engineering group but wasn't validated by their
                 operations team. During start-up the operations demanded scope changes because the project scope
                 didn’t align with how they intended to operate the facility. Require operations engagement during
                 the design review and scope development process to align expectations prior to execution.


                 WORK IN OPERATING FACILITY

                 The project was implemented in multiple operating manufacturing facilities. The schedule for the
                 project didn't adequately reflect the operational constraints that existed. The client had to continue
                 delivering product to their business despite the disruptions caused by the construction and installation
                 activities. Work with operations team during the schedule development process. Include schedule
                 contingency to accommodate flexibility to manage through operational constraints. Provide senior
                 leadership on site to lead the execution team and manage operations interface full time.



                 START-UP AND TESTING BUDGETING

                 The start-up and testing plan was not developed prior to finalizing the contract scope and schedule. When the
                 start-up and testing plan was finalized in order to validate system performance and conformance with performance
                 guarantees, there were issues with responsibilities as well as challenges scheduling the required testing. The
                 client could not adapt the production schedule to meet the testing requirements. Further, they couldn't fulfill
                 their responsibilities, including, supplying qualified operators and materials per the required specifications. This
                 led to frustrations and cost increases for both Haskell and Diageo. Including start-up as an allowance is best
                 practice as it's typically not feasible to finalize start-up and testing schedule at the time of initial GMP.
                 Defer finalizing start-up costs until reaching final alignment on the start-up and testing schedule.












        46                                                                               MEGA PROJECTS PLAYBOOK | 2021
                                CONTAINS CONFIDENTIAL AND PROPRIETARY INFORMATION.  FOR INTERNAL HASKELL USE ONLY.
   46   47   48   49   50   51   52   53   54   55   56