Rolling stock speed improvements
                        Processing  for  increasing  wagon  speeds  where  JSC  speeds
                          are less than that of wagon permitted speeds.

                          A total of 40 type wagons were identified and letter was sent
                          to  Sr.DEN/CO-ord  /SC  to  enhance  the  speeds  over  30
                          sections of SC division
                          (Annexure Enclosed)


                        Increasing  the  speeds  of  11  different  track  maintenance
                          machines to RDSO/IRTMM permitted speeds is under process

                          (Annexure Enclosed)







               i.   Coaching:


                        334 Numberr of VPU/VPH ‘s (Indent) were attached to various
                          trains,  in  addtion  to  leased  VPU/VPH’s  up  to  October  –  22

                          and earned an revenue of Rs.4.93crores
                        On day  to day  basis, to clear extra rush of  passengers,  632
                          additional  coaches  were  attached  as  extra  rush,  538
                          coaches were augmented. And also 586 special trains were
                          run for 1738 trips up to the October – 22.
                        Speed of LBH coaches is enhanced to 130kmph, 22 outgoing

                          trains and 16 incoming trains are run with 130kmph regularly.
                        A  total  18.36kms  03rd  line  completed  up  to  October  –  22
                          between BGSF-OPL stations




               4. Operational Infrastructure improvement underway


                       Operational Infrastructure sanctioned:


                   a) PDPL bypass at KZJ end:

                          Sanctioned  3   line  works  between  KZJ-BPQ  under  material
                                             rd
                          modification.(Construction)



                          Status:  Drawings  and  alignment  is  approved.  Estimates
                          prepared.  Needs  to  be  included  for  material  modification
                          and fund allocation.