Page 131 - GM E-BOOKLET 2022
P. 131
B. GATI SHAKTI TERMINALS In pipe line
Proposed
S. No. Status
GCT
FSR approved on 17.5.22, IPA issued, ESP
SUH-Kodla
1 approved on 11.10.22. DPR to be submitted by
plant
consultant.
ESP Approved on 13.05.2022, revised DPR
VKOC CHP-
2 approved on
BDCR
21.09.22. Tenders to call.
ESP and DPR approved, Consultant submitted
3 BTPS-MUGR BTPS-CSP connectivity ESP at CE.P&D for
approval.
FSR, IPA and ESP are approved. Environmental
Dalmia clearence received from State government.
4 Cements- Mining lease lapsed. Petition filed in High
MQR-SEM court/Karnataka. 90% of land acquisition
completed.
Tata Steels – ESP approved on 17.06.2022, Revised DPR to be
5
NPL submitted by the consultant.
RITES to upload Sheet 2&3 in E-Das for approval.
KK SCCL – GM/Civil/SCCL on 22.6.22 meeting requested to
6
BPA keep the proposal live for 02 years as coal blocks
are not alloted to SCCL.
IPA issued on 09.07.21. Observations on revised
Varalakshmi
7 plan sent to consultant on 18.02.22. Financial
– OPL
disputes.
IPA issued on 09.04.22. Consultant has to submit
8 Medha – NPL
ESP & DPR.
IPA issued on 04.08.21. Consultant has to submit
9 NCL – SSLM
ESP & DPR. Forest clearance yet obtain.
129