CONSTRUCTION BUDGfT PROJECT: ACME MANUFACTURING
Division Heading/Item Quantity Unit Cost
1000 General
Casual Labor 20 hrs./wk. $15./hr.
Site trailer rental 5 mths. $340./mth.
Telephone 5 mths $100./mth.
Water 5 mths. $60./mth.
Temporary electric service Ls $800.
Sanitary rental unit 5 mths $100./mth.
Site sign 2 @ $175./ea. $350.
Storage trailer rental 5 mths. $200./mth.
Fencing/hoarding Ls $500.
Fuel/energy costs Ls $500.
Refuse dumpsters 6 x 20 cy @ $375./ea. $2250.
Cleanup labor 10 hrs./wk. max. $12./hr.
Cleanup trucking 3 loads @ $150 loaded/dumped $450.
Final interior/exterior cleaning Ls $1800.