CONSTRUCTION BUDGfT PROJECT: ACME MANUFACTURING
Division Heading/Item Estimated Quantity Unit Cost
4000 Masonry
Brick 10000 units $550./1000
Install $1200./1000
Misc. ties etc. $225.
5000 Metals
Structural steel 21T supply/erect $2000./T
Roof deck x 3500 sf $1.50/sf
Floor pan x 3500 sf $1.00/sf
Anchor bolts x 78 matl. $8./ea.
Miscellaneous Stairs (2) subcontract
Ladder x 1 $600
Bollards x 4 $200./ea.