CONSTRUCTION BUDGfT PROJECT: ACME MANUFACTURING
Division Heading/Item Estimated Quantity Unit Cost
7000 Moisture Protection
Foundation insulation 2: rigid x 1060 sf $1.50
Wall batts R20 x 5540 sf $.65/sf
Blanket insulation R20 x 24120 sf $.80/sf
Acoustical 4”/6” x4000 sf $.55/sf
Wall rigid 1” x 1800 sf $.75/sf
BUR 3500 sf x subcontractor $20000
Curbs X 4 $125./ea.
Gutters/downspouts 300 lf $12./lf
Metal siding 2400 sf $4./sf
Fascia x 200 lf $4.50/lf
Caulking Subcontract $1200.