Page 294 - TCDB combined Book
P. 294

272                      The Complete DESIGN BUILDER








               Project Schedule:


                       On most projects a preliminary schedule or length of time to complete will be established
               prior to commencing the work.  Depending on the size and complexity of a project the type of
               schedule will vary.  We offer the following types for your consideration.


                   Bar Chart


                   Critical Date




               Bar Chart Schedule:


                       A Bar-Chart type schedule is the most common and simplest form available.  Prior to
               preparing your schedule, confirmation of delivery dates for major purchase items and
               subcontractor input on allotted time requirements should be finalized.  Upon completion of the
               schedule and agreement by all affected parties, distribute to all concerned and prominently display
               this schedule on-site.  Monitoring and updating the schedule as work progresses is mandatory and
               should help identify the reasons when not on schedule.  Regular on-site meetings with
               subcontractors and any affected parties are critical to solving scheduling problems.




               Critical Date Schedule:


                       A Critical-Date Schedule is used on large or more complex projects.  This type of schedule
               can be divided into a number of mini-schedules covering various portions of the work, then used
               by the individual subcontractors, in place of the main schedule.  The critical dates for delivery of
               major items or start and completion dates for the activities are the basis for this schedule.  The
               critical nature of this type of schedule is its dependency on the input date information. More
               intensive consultation with your subcontractors and suppliers will be required prior to finalization.
               As for any type of schedule the importance of continual monitoring and updating as the work
               progresses is of utmost importance.  Prominently display your current schedule and promptly
               advise, in writing, any parties failing to meet their scheduled commitments.
   289   290   291   292   293   294   295   296   297   298   299