                     CONSTRUCTION BUDGfT                                 PROJECT: ACME MANUFACTURING


               Division          Heading/Item                 Estimated Quantity               Unit Cost

               8000       Doors and Windows

                          HMD/PSF                                Supplier order                 $4000.


                          SCWD/PSF                               Supplier order                 $4000.

                          Hardware                             Purchase allowance               $8000.


                                                                  Install x 36                 $75./ea.

                          Commercial aluminum                 x 3 units subcontract             $5400.

                          Overhead                            x 2 units subcontract             $4800.




                          Commercial windows                      Subcontract                  $18000.




               9000       Finishes


                          Steel stud drywall                     Subcontractor                  $32000.

                          Suspended ceilings                     Subcontractor                 $17000.

                          Flooring                                Subcontract                   $18640.


                          Painting                                Subcontract                   $10000.