Chapter  5     CONSTRUCTION             267



                                                                          l�L   CONSTRUCTION
                                                                           YOUR   COHPLETE  DESIGN-BUILDER

                     CONSTRUCTION BUDGfT                                 PROJECT: ACME MANUFACTURING


               Division          Heading/Item                 Estimated Quantity               Unit Cost

               6000       Woods and Plastics

                          Rough carpentry                 Mezz.  Floor. x 1320 sf matl.         $4000.



                                                                     Install                    $2000.


                                                                Blocking/backing                 $700.


                                                              Roof parapet x 240 lf              $6./lf




                          Finish carpentry                    Stairs to mezz. x 14 R            $35./R


                                                            Railing at mezz. x 144 lf            $3./lf

                                                               Hardwood handrail                $$575.

                                                               Closet shelvingrods               $250.

                                                               Fasteners/anchors                 $150.




                          Millwork                             Kitchenette x 8.0 ft.            $1000.

                                                                  Vanities x 4                  $1560.


                                                                  Counters x 2                   $630.


                                                               Fasteners/anchors                 $100.
   284   285   286   287   288   289   290   291   292   293   294