Chapter 5 CONSTRUCTION 267
l�L CONSTRUCTION
YOUR COHPLETE DESIGN-BUILDER
CONSTRUCTION BUDGfT PROJECT: ACME MANUFACTURING
Division Heading/Item Estimated Quantity Unit Cost
6000 Woods and Plastics
Rough carpentry Mezz. Floor. x 1320 sf matl. $4000.
Install $2000.
Blocking/backing $700.
Roof parapet x 240 lf $6./lf
Finish carpentry Stairs to mezz. x 14 R $35./R
Railing at mezz. x 144 lf $3./lf
Hardwood handrail $$575.
Closet shelvingrods $250.
Fasteners/anchors $150.
Millwork Kitchenette x 8.0 ft. $1000.
Vanities x 4 $1560.
Counters x 2 $630.
Fasteners/anchors $100.