CONSTRUCTION BUDGfT PROJECT: ACME MANUFACTURING
Division Heading/Item Estimated Quantity Unit Cost
1000 General
As builts Ls $300.
Reproduction costs Ls $500.
Photography 5 mths. $100./mth.
Shop drawings ls $800.
print/distribution
Misc. tools Ls $800.
Misc. rentals Ls $1200
2000 Site Work
Strip topsoil 711 cy $1./cy
Haul topsoil on site 356 cy $.50/cy
Excavate 711 cy $3./cy
Haul excavated surplus 356 cy $3./cy
Backfill foundations Import 400T @$4./T + place $6./T
Backfill using excavated place 400T $3./T
Underslab fill Import 1541T @ $5./T avg. + place $7./T