CONSTRUCTION BUDGfT PROJECT: ACME MANUFACTURING
Division Heading/Item Estimated Quantity Unit Cost
3000 Concrete
Expansion joint 3”/4”/6”/ x 840 lf $800.
Bulkhead
Concrete $500
Place/form/strip $5.lf
Concrete pump 8 hrs. $150./hr.
Anchor bolts Install 36 sets $25./hr.
4000 Masonry
Load bearing 1700 x 8” matl. $2.50 /ea.
install $3./ea.
2000 x 4” split face matl. $3.50./ea.
Install $3.50./ea.
Rebar .8T $800./T
Blok-lok x 2400 lf $.35/lf
Concrete fill x 10 cy $100./cy
Sealer x 3000 sf $.20./sf