Page 6 - HSSE Contractor Requirement
P. 6
HSSE REQUIREMENT FOR CONTRACTOR, ALLO TECHNOLOGY
EDITION 01
II. Upon receipt of any such notice, the Contractor shall, unless instructed otherwise:
a. discontinue the work or the part of the work as specified by the Employer, on the date and
to the extent specified by the Employer;
b. properly protect and secure the work as required by the Employer;
c. take all reasonable measures to minimize the costs and losses of the Employer and the
Contractor, including placing no further orders and making no further subcontracts with
respect to the suspended portion of the work other than as specified in the notice;
d. promptly make every reasonable effort to obtain suspension upon terms satisfactory to
the Employer of all outstanding orders and subcontracts to the extent they relate to the
execution of the portion of the work suspended;
e. not remove from the worksite any construction equipment or materials without the prior
consent of the Employer; and
f. continue to perform all unsuspended parts of the Contract.
III. In the event of default on the part of the Contractor and before the suspension of the work by
the Employer, the Employer shall give notice of default to the Contractor or giving details of
such default.
IV. If the Contractor, upon receipt of such notice, does not commence immediately or proceed
with action satisfactory to the Employer to remedy such default within the period stated in
the Employer’s notice, the Employer may issue a notice of suspension.
V. Unless the suspension arises as a result of default on the part of the Contractor, the Contract
Price and programme shall be adjusted in accordance with the agreed schedule of rates and
program approved by the Employer.
VI. If suspension is due to default on the part of the Contractor, any additional costs incurred by
the Employer resulted from the suspension shall be recoverable by the Employer from the
Contractor.
VII. The Employer may, by further notice, instruct the Contractor to resume the Work to the extent
specified.
VIII. In the event of any suspension, the Employer and the Contractor shall meet at not more than
seven (7) days intervals with a view to agreeing a mutually acceptable course of action during
the suspension.
b) Health, Safety, Security and Environmental (HSSE)
I. The Employer places utmost importance on Health, Safety, Security and Environmental issues
and requires that the Contractor subscribes to and actively pursues the highest standards of
HSSE performance. The Contractor confirms that it (together with its subcontractors and their
affiliates) have adequate written HSSE policies as per the Employer’s requirements.
II. The Contractor shall take full responsibility for the adequacy, stability and safety of all of the
Contractor’s operations and methods necessary for the performance of the work and shall
comply to the provisions of this requirement. The Contractor shall collaborate with the
Employer in establishing HSSE interface arrangements and the production of an HSSE interface
document.