Page 6 - HSSE Contractor Requirement
P. 6

HSSE REQUIREMENT FOR CONTRACTOR, ALLO TECHNOLOGY
                                                                                                   EDITION 01



                     II.   Upon receipt of any such notice, the Contractor shall, unless instructed otherwise:
                          a.  discontinue the work or the part of the work as specified by the Employer, on the date and
                              to the extent specified by the Employer;
                          b.  properly protect and secure the work as required by the Employer;
                          c.  take all reasonable measures to minimize the costs and losses of the Employer and the
                              Contractor, including placing no further orders and making no further subcontracts with
                              respect to the suspended portion of the work other than as specified in the notice;
                          d.  promptly make every reasonable effort to obtain suspension upon terms satisfactory to
                              the Employer of all outstanding orders and subcontracts to the extent they relate to the
                              execution of the portion of the work suspended;
                          e.  not remove from the worksite any construction equipment or materials without the prior
                              consent of the Employer; and
                          f.  continue to perform all unsuspended parts of the Contract.

                    III.   In the event of default on the part of the Contractor and before the suspension of the work by
                          the Employer, the Employer shall give notice of default to the Contractor or giving details of
                          such default.
                    IV.   If the Contractor, upon receipt of such notice, does not commence immediately or proceed
                          with action satisfactory to the Employer to remedy such default within the period stated in
                          the Employer’s notice, the Employer may issue a notice of suspension.
                     V.   Unless the suspension arises as a result of default on the part of the Contractor, the Contract
                          Price and programme shall be adjusted in accordance with the agreed schedule of rates and
                          program approved by the Employer.
                    VI.   If suspension is due to default on the part of the Contractor, any additional costs incurred by
                          the Employer resulted from the suspension shall be recoverable by the Employer from the
                          Contractor.
                    VII.   The Employer may, by further notice, instruct the Contractor to resume the Work to the extent
                          specified.
                   VIII.   In the event of any suspension, the Employer and the Contractor shall meet at not more than
                          seven (7) days intervals with a view to agreeing a mutually acceptable course of action during
                          the suspension.

                   b)    Health, Safety, Security and Environmental (HSSE)
                      I.   The Employer places utmost importance on Health, Safety, Security and Environmental issues
                          and requires that the Contractor subscribes to and actively pursues the highest standards of
                          HSSE performance. The Contractor confirms that it (together with its subcontractors and their
                          affiliates) have adequate written HSSE policies as per the Employer’s requirements.
                     II.   The Contractor shall take full responsibility for the adequacy, stability and safety of all of the
                          Contractor’s operations and methods necessary for the performance of the work and shall
                          comply  to  the  provisions  of  this  requirement.  The  Contractor  shall  collaborate  with  the
                          Employer in establishing HSSE interface arrangements and the production of an HSSE interface
                          document.