GENERAL ELECTRICAL SPECIFICATION
                                 Version 2014-2



                         The Electrical Contractor shall use the standard disk as a basis for the Health & Safety File
                         for the project containing:

                          •  An edited tick list indicating the plant and equipment installed
                          •  Any plant and equipment used on the project and not on the st andard tick list shall
                              be added to the end of the lists
                          •  Technical data and manufacturers details for plant and equipment from the standard
                              list, where used on the project
                          •  Scanned technical data and manufacturers details for plant and equipment used, not
                              on the standard list
                          •  Scanned versions of any test sheets produced for the installations

                          •  As installed drawings in Autocad format

                         A copy of the completed disc together with a single hard copy of all information contained
                         in the binder shall be issued to the Project Planning Supervisor. A further copy of the disk
                         shall be issued to the Consulting Engineer for comment
                         Any revision arising from comments received shall be issued on a revised disk, with the
                         revised pages issued to the Planning Supervisor.

               1.2.6  Programme and Progress Chart

                         The Electrical Contractor shall be required to coordinate the MEP works with the overall
                         programme.

                         The Electrical Contractor is to, within two weeks of acceptance of his Tender prepare and
                         submit to the Project Manager for review and comment a detailed time and progress
                         chart, together with a design/ installation drawing production programme showing in
                         detail the duration and completion of all parts sections, disciplines and operations,
                         including the labour force anticipated day by day.

                         The  Electrical Contractor is to,  at the same time, prepare and submit to the Project
                         Manager an order/delivery schedule, showing all plant and equipment for incorporation
                         into a typical Works package.

                         The Electrical Contractor shall identify in the programme when it may be necessary as
                         part of the works to interrupt the maintained services for the approval of the Project
                         Manager.  This is to be submitted in good time to allow full Client consultation.

                         Method statements are to fully detail the proposed services to be worked on, the method
                         by which work is to be carried out including "fall back" procedures and a full programme
                         with critical timescales highlighted.