GENERAL ELECTRICAL SPECIFICATION
                                 Version 2014-2



               1.2.7  Builderswork


                         All bases, holes through structures, positions for brackets, chases etc, are to be detailed
                         by the  Electrical Contractor  either on drawings submitted in accordance with dates or
                         agreed by marking out on site in advance. The  Electrical Contractor is to be fully
                         responsible for the correct positioning.
                         Where the formation of holes, cutting away etc, might adversely affect the building
                         structure, drawings detailing those requirements are to be prepared by the Electrical
                         Contractor and submitted to the Project Manager (PM) for approval.

                         The Electrical Contractor is to provide all necessary fixing devices.  Where brackets require
                         to be built into the structure, sufficient detailed drawings or templates for all items
                         requiring foundation bolts or other fixtures and for all plant required to be built into, or
                         otherwise affecting the structure are to be provided for comment by the design team.

                         The  Electrical Contractor is to ensure that the foundation levels for plant, bedding or
                         grouting in of plant on foundations and bases, and grouting in of other fixings are
                         adequately and properly performed.

                         The  Electrical Contractor shall arrange for the construction of all builders work ducts,
                         excavation, back filling and reinstatement of all trenches, including the installation of
                         service marker posts.  The Electrical Contractor is to detail the routes of these services on
                         dimensioned drawings submitted to the PM for approval.   These drawings are to form
                         part of the project CDM file and are to be made available immediately after the service
                         has been laid.  The drawings are to ultimately be incorporated in the O & M Manuals.

                         The  Electrical Contractor  is to make allowance for the supply and installation of fire
                         stopping of all trunking, trays, pipework, ductwork and for all equipment and services
                         passing through fire compartments.
               1.2.8  Site Meetings and Reports


                         The Electrical Contractor is to have a representative in attendance when required at any
                         site meetings.  The M & E Coordinator is to be fully conversant and familiar with the scope
                         and details of the Contract, the Contract programme, labour resources etc., and be
                         authorised to take any action and make any decision necessary.  The Electrical Contractor
                         is to allow at least one day a week for this purpose.
               1.2.9  Protection and Handling


                         All works, both during and after installation, until the completed project is handed over to
                         the Client, are to be suitably and adequately protected against damage by other trades or
                         by water or frost.  Such protection is to be dismantled and removed from site immediately
                         prior to handover.