Page 26 - RotF - Electrical Specification_Neat
P. 26
GENERAL ELECTRICAL SPECIFICATION
Version 2014-2
1.2.7 Builderswork
All bases, holes through structures, positions for brackets, chases etc, are to be detailed
by the Electrical Contractor either on drawings submitted in accordance with dates or
agreed by marking out on site in advance. The Electrical Contractor is to be fully
responsible for the correct positioning.
Where the formation of holes, cutting away etc, might adversely affect the building
structure, drawings detailing those requirements are to be prepared by the Electrical
Contractor and submitted to the Project Manager (PM) for approval.
The Electrical Contractor is to provide all necessary fixing devices. Where brackets require
to be built into the structure, sufficient detailed drawings or templates for all items
requiring foundation bolts or other fixtures and for all plant required to be built into, or
otherwise affecting the structure are to be provided for comment by the design team.
The Electrical Contractor is to ensure that the foundation levels for plant, bedding or
grouting in of plant on foundations and bases, and grouting in of other fixings are
adequately and properly performed.
The Electrical Contractor shall arrange for the construction of all builders work ducts,
excavation, back filling and reinstatement of all trenches, including the installation of
service marker posts. The Electrical Contractor is to detail the routes of these services on
dimensioned drawings submitted to the PM for approval. These drawings are to form
part of the project CDM file and are to be made available immediately after the service
has been laid. The drawings are to ultimately be incorporated in the O & M Manuals.
The Electrical Contractor is to make allowance for the supply and installation of fire
stopping of all trunking, trays, pipework, ductwork and for all equipment and services
passing through fire compartments.
1.2.8 Site Meetings and Reports
The Electrical Contractor is to have a representative in attendance when required at any
site meetings. The M & E Coordinator is to be fully conversant and familiar with the scope
and details of the Contract, the Contract programme, labour resources etc., and be
authorised to take any action and make any decision necessary. The Electrical Contractor
is to allow at least one day a week for this purpose.
1.2.9 Protection and Handling
All works, both during and after installation, until the completed project is handed over to
the Client, are to be suitably and adequately protected against damage by other trades or
by water or frost. Such protection is to be dismantled and removed from site immediately
prior to handover.
McDonalds Restaurants Ltd
4