Drainage & Piped Services Standard Specification
Version 2014-1
no cost to the Client providing that the Contractor is not required to correct any defect
due to normal wear and operation.
The Contractor shall be required to provide a fully detailed written report to the Project
Manager of each and every such defect together with the remedial works undertaken
within seven days of such remedial works.
1.2.47 Public Health
The Contractor is to supply, install and provide 'as installed' record drawings and
operation & maintenance manuals, commission and demonstrate as applicable, all the
necessary materials, components and equipment to form a complete working
installation at the premises in accordance with all relevant British and European
Standards. The completed installation, new and existing services adapted as part of the
contract are to be fully in accordance with all relevant BS/EN Regulations and local
authority requirements.
The Contractor is to be responsible for identifying and making suitable provision for,
the mechanical characteristics of all materials, equipment and components as specified
or having an impact upon the design or performance of the mechanical services
installation.
The Contractor is to be responsible for identifying at an early stage; the delivery period
associated with all equipment and is to satisfy himself that these can be procured
within the constraints of the construction programme, without adverse effect on the
project.
Should the Contractor identify any potential problems these are to be reported as soon
as is practicably possible.
Where information on the services in any area is not provided, it is the responsibility of
the Contractor to select equipment, materials and components, suitable for the
application and thereafter design and install an adequate layout, with due
consideration of the usage of the space.
Any omission from the tender in this regard, are to be clearly and unequivocally stated
and highlighted within the tender submission.
The Contractor is to produce detailed working installation drawings, fully co-ordinated
in every respect in terms of distribution routes and equipment locations, with the
installation components etc., of all other services and building disciplines.
It is to be the responsibility of the Contractor to satisfy himself that all mechanical plant
and equipment sizes provided to him in the tender documentation are of adequate size
for the installations for which they serve. This is to include, but not limited Pipework,
Pumps, Heaters etc.
It is to be the responsibility of the Contractor to satisfy himself that all plantrooms and
ducts/cupboards etc. shown for the routing/positioning of mechanical services and
McDonalds Restaurants Ltd 1 / 19