Page 10 - LINK - Workflow - B3937-AEW-XX-XX-R-A-001
P. 10

DOMINO’S PIZZA GROUP                                                                                                                               AEW ARCHITECTS





       FORESHORTENED WORKFLOW - SCENARIO 3




       The next approach to the workflow would be to overlap Stages 1, 2, 3 + 4 as     This would allow earlier submission of any change of use application required to the
       demonstrated below. Stage 5 would continue to run sequentially following successful   LPA as scenario 1 but also provide an earlier route to submitting secondary applications
       completion of Stage 3 + 4.                                                      (such as Advertisement, Listed Building etc) to the LPA. The limitation of this process
                                                                                       is that any discharge of condition applications which may be required cannot be
                                                                                       completed until the original approval is in place.







                  TASK / WEEK                                  1      2      3      4       5      6      7      8      9      10     11     12     13     14                   15     16     17     18     19     20     21     22      23     24     25     26     27     28     29     30     31     32     33     34      35     36
                  NSC

       STAGE 1    Measured survey
                  Feasibility scheme
                  Site briefing meeting
                  Updated prelim and briefing minutes
                  Franchisee approval

       STAGE 2    Production of change of use information
                  LPA COU application (av 10 weeks)

       STAGE      Shopfitting drawings
       3 & 4      Building regulation application
                  Advertisement application
                  LPA advertisement application (av 10 weeks)
                  ‘Other’ applications (listed building)
                  LPA ‘other’ application (av 10 weeks)
                  Condition discharge
                  LPA ‘condition discharge’ (no fixed timescale)

       STAGE 5    Pre start meeting
                  Mobilisation
                  Start on site
                                                         NSC   STAGE 1: 6 WEEKS  STAGE 2: 12 WEEKS
                                                                             STAGE 3 + 4: 14 WEEKS
                                                                                  STAGE 1 / 2 / 3 + 4 OVERLAP    STAGE 2 / 3 + 4 OVERLAP
       10
   5   6   7   8   9   10   11   12   13   14