       Risk in this scenario is limited to the overlap between Stages 1 and 2. The maximum
       financial value of this risk would be the cost of completing Stage 2 for a second time.
       Architecturally this is £600 but other professional fees should be considered such as
       external Planning Consultants.

       This system would continue to allow DPG to remain anonymous through the change of
       use application process.




 TASK / WEEK  1  2  3  4  5  6  7  8  9  10  11  12  13  14  15  16  17  18  19  20  21  22  23  24  25  26  27  28  29  30  31  32    33     34     35     36
 NSC

 STAGE 1  Measured survey
 Feasibility scheme
 Site briefing meeting
 Updated prelim and briefing minutes
 Franchisee approval
 STAGE 2  Production of change of use information
 LPA COU application (av 10 weeks)
 STAGE   Shopfitting drawings
 3 & 4  Building regulations application
 Advertisement application
 LPA advertisement application (av 10 weeks)
 ‘Other’ applications (listed building)
 LPA ‘other’ application (av 10 weeks)
 Condition discharge
 LPA ‘condition discharge’ (no fixed timescale)
 STAGE 5  Pre start meeting
 Mobilisation
 Start on site
       STAGE 3 + 4: 14 WEEKS                                                                              STAGE 5: 4 WEEKS


                                                                                                                                                                   7
   2   3   4   5   6   7   8   9   10   11   12