Page 9 - LINK - Workflow - B3937-AEW-XX-XX-R-A-001
P. 9
DOMINO’S PIZZA GROUP AEW ARCHITECTS
If there are no conditions to discharge then this scenario could save 12 weeks from the Risk in this scenario is increased to conflict between the Stage 2, 3 + 4 steps. The
current workflow, resulting in a 24 week process. Where conditions are required to be maximum financial value of this risk would be the cost of completing Stage 2 and all of 3
discharged then this scenario would save 3 weeks from the current workflow, resulting in + 4 for a second time. Architecturally this could range between £3,455 – £4,175 but other
a 33 week process. professional fees should be considered such as external Planning Consultants, LPA fees
and Structural Engineers.
This system would NOT allow DPG to remain anonymous through the change of use
application process.
TASK / WEEK 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36
NSC
STAGE 1 Measured survey
Feasibility scheme
Site briefing meeting
Updated prelim and briefing minutes
Franchisee approval
STAGE 2 Production of change of use information
LPA COU application (av 10 weeks)
STAGE Shopfitting drawings
3 & 4 Building regulations application
Advertisement application
LPA advertisement application (av 10 weeks)
‘Other’ applications (listed building)
LPA ‘other’ application (av 10 weeks)
Condition discharge
LPA ‘condition discharge’ (no fixed timescale)
STAGE 5 Pre start meeting
Mobilisation
Start on site
STAGE 5: 4 WEEKS
STAGE 2 / 3 + 4 OVERLAP
9