Page 8 - Bernardon Proposal-Progressive New Homes
P. 8
www.bernardon.com
We will document the project as a 3D Revit ■ Drawings:
model that will be used for the life of the project o Overall floor and ceiling plans;
for Construction Documents and coordination o Overall roof plan;
with our consultants. The following tasks and o Exterior elevations;
deliverables will be provided during this phase: o Building sections;
o Typical wall sections;
■ Four (4) Meetings: o Enlarged unit plans;
o Project kick-off meeting; o Door and window schedules;
o Progress design review meeting; o Structural engineering plans and
o One (1) meeting with local jurisdiction; and details; and
o Schematic Design review meeting. o MEPFP plans, riser diagrams, and details.
■ Technical specifications (Book Format).
■ Drawings:
o General information with code summary; Four (4) Design Review and Coordination meetings
o Overall floor plans with unit layouts; have been included in this phase.
o Colored building elevations;
o Overall building section;
o Structural basis of design narrative; and Phase III – Construction Documents (10 weeks)
o MEPFP basis of design narrative. With your approval of the Design Development
set of documents, we will prepare documents
Phase II – Design Development (8 weeks) suitable for final bidding, permitting, and
The approved solutions created during the construction as follows:
Schematic Design process shall form the base
information to proceed with Design Development ■ Drawings:
documents. Minor ongoing design review o Architectural floor plans for each floor
comments will be incorporated into the design as and roof;
this phase proceeds. Prior to our meetings, we will o Enlarged plans and details of each unit;
assess the ramifications of the proposed changes o Building elevations;
or improvements as they relate to structural, code, o Wall sections;
systems, and cost implications. We will prepare o Exterior and interior details;
documents for preliminary pricing and distribute o Schedule for doors, hardware, and
them to you for review and critique. The goal will plumbing fixtures;
be to finalize the architectural relationships and o Stair sections and details;
determine structural implications. We will provide o Elevator plans and sections;
the following Design Development documents at o Structural plans and details; and
the conclusion of this phase: o MEPFP plans and details.
■ Technical specifications (Book Format).
Four (4) Design Review and Coordination meetings
have been included in this phase.
BERNARDON | Response to Request for Proposal