Page 15 - Chemical Tire Applicator™ / Wheel Brite Applicator™
P. 15
CHEMICAL TIRE APPLICATOR™
WHEEL BRITE APPLICATOR™
Installation
Tank and Frame Assembly
1) Position tank and frame assembly on equipment room wall 54” above floor. This will allow for
placement of most chemical drums.
2) Level unit and fasten to wall (fasteners not supplied by Belanger, Inc.). Make sure structure is
rigid.
Air pressure Wall mounted air panel
adjustment Pump (right side)
Main air supply
80-PSI maximum Pump
Pump
“MATERIAL IN”
Air regulator feed from tank
“MATERIAL OUT”
Feed to treadle
Hydrominder™ Water inlet valve
Main water feed
Suction hose, Suction hose
Feed from Feed to pump
chemical drum, (left side)
(replaceable “MATERIAL IN”
orifice located
here)
Strainer with foot valve
Float
Lab cock valve
1MANUL088 Belanger , Inc. * 1001 Doheny Ct. * Northville, MI 48167 * Ph (248) 349-7010 * Fax (248) 380-9681 13