Page 26 - Final Report - KAUSC Team
P. 26
KAUSC Team
Risks
Any event, which may adversely affect the ability of the solution to produce the required
deliverables. That was the definition of the Risks. The table below shows the risks that may
affect this option.
Table 17 risk of option 3
Description Likelihood Impact© Mitigating Actions
Roll over action Low Very Train the driver to control the car in
High extreme situations (ex. Windy
Different day..etc.)
environment Medium High
Training the team for emergencies.
conditions Medium High
High temperature Low Emergency circuit for monitoring the
Very batteries to stop them
of batteries High
Outsource project to a company with
Inability to recruit proven industry experience and
skilled resource appropriately skilled staff
Issues
Any event, which currently adversely affects the ability of the solution to produce the
required deliverables. That was the definition of issue. The table shows issues that are more
likely to happen.
Table 18 issues of option 3
Description© Priority Resolution Actions
No workshops to manufacturing
High Self-manufacturing
the car
Medium Change the material that is available in
No material available Low local market
High Lend money.
Financial lack
Inability to manufacture parts Use exist parts from similar cars
Assumptions
Assumption are a guessing of some information that are fix during the designing of the
project:
Prices of raw materials will not change during the course of this project.
Parts are available in the local market with standers.
25 | P a g e